Systems / Experimental discovery
Production laboratory
Investigate three stations, schedule six operations, and adapt your plan to an outage.
Discover three stations, then schedule six jobs twice with the same station assignments. Scenario 2 closes station 3 from time 3 to 5.
D follows A, E follows B, F follows C. A material change adds one setup tick and one solvent unit. Power ≤3, solvent ≤8, wait after predecessor ≤6. Finish by 10 normally and 12 during the outage.
Experiment bench
Need a hint?
Station 2 uses power 1 and takes amber 3 / mint 2. Station 3 uses power 1 and takes either material 2. A changeover adds 1. Using those two stations avoids the shared power bottleneck.
Schedule monitor
S1
A0–2
D0–4
S2
B0–3
E0–3
S3
C0–2
F0–2
Finish time4
Peak power8 / 3
Solvent7 / 8
Timeline shows ticks 0–25. Blocks include any changeover. Amber and mint also carry text labels in the editor below.
Dispatch editor
| Job / material | After | Station (both scenarios) | Normal start | Outage start |
|---|---|---|---|---|
| A · amber | — | |||
| B · amber | — | |||
| C · mint | — | |||
| D · mint | A | |||
| E · amber | B | |||
| F · mint | C |
Explore the controls, then check your result.